NTCRA – Completed Activities

October 2016 – Present

  • Since completion of Building Demolition, the site has been routinely inspected and maintained. Monthly Inspections are performed to ensure security measures (i.e. fences, alarm systems, etc.) are in check, building liners are not damaged, and site controls are maintained. There have been no significant issues noted during the inspection periods.

September 2016

  • Equipment to remain on site received final maintenance and preparation for long term storage. de maximis performed Post-Site Control Activities through the month and installed a security system on remaining trailers.

August 2016

  • Installation of the liners over all the Building Slabs was completed, as was all site restoration efforts involved with the Demolition Work Plan. As part of the Demolition Work Plan, subcontractors terminated the fire loop and removed all terminated hydrants.
  • The demolition contractors demobilized from the site and remaining equipment was surveyed, characterized and free released.
  • Shipping and disposal of building debris was completed, totaling 912 intermodal shipment to US Ecology, totaling 23.5 million lbs. Building Demolition specific shipments totaled 479 trucks and 14.99 million lbs of debris

July 2016

  • Building Demolition was completed; Buildings A, B and E were removed and installation of the temporary liner was completed over these areas. Additional removal efforts included excavation and disposal of the underground storage tanks.

June 2016

  • Continued Building Demolition activities; Buildings B and Butler B4 were completed. Included in the process was the filling and capping of the Building B basements and elevator pits. Approximately 80% of Building E was removed during the month.
  • Installation of the temporary slab liner continued throughout the Building C, and preparations began on the Building B, B4 and E slabs for installation of the liner.
  • The remaining oil and sludge from the underground storage tanks was removed, and preparations began to allow for easy removal of the tanks

May 2016

  • Continued Building Stabilization activities, including the removal of ACM transite panels from Buildings A, B, and C.
  • Continued Building Demolition activities; by the end of May, Buildings C, D and Butler B4 were demolished and packaged in intermodals for offsite disposal at USEI. Installation of the temporary cover over Buildings C and D began.
  • Through the end of May, 122 intermodals of demolition debris had been shipped off site to US Ecology Idaho for land disposal, totaling 3,788,810 pounds (1894 tons).

April 2016

  • Continued Building Stabilization activities, including completion of cutting and resizing of remaining building equipment using burn bars, terminated the electrical and natural gas service to the building, installed a 12-inch shut off valve on the fire suppression waterline as requested by the Concord Water department, continued installation of the Water Treatment System, and commenced ACM panel abatement from the eastern side of Building C.
  • Commenced building demolition activities on 19 APR 2016 and by the end of April, about 50% of Building D was removed.
  • Continued Transportation and Disposal activities, including completing a minor lab-pack on 11APR removing the remaining batteries, lead, and PCB ballast. US Ecology mobilized to the
  • One health and safety incident occurred during the month of April and the Concord Police and Fire Department responded to assist a subcontractor worker injured during site work. The individual is now back to work.

February 2016

  • Continued Building Stabilization activities, including final cleaning and lock down in Building D; loaded seven intermodal containers with remaining contaminated debris for final loading campaign prior to demolition.

January 2016

  • Continued Building Stabilization activities, including: sealing remaining cracks and floor penetrations; mobilized the water treatment building and constructed a temporary foundation for it; cleaned and decontaminated the Frac-tank and relocated to the water treatment system building location; completed interior radiological surveys of buildings and support structures; completed application of lock-down and floor sealant in Buildings A, B, and E.
  • Provided a site tour to the Concord Assistance Fire Chief on 13 JAN and deactivated the buildings fire suppression system and alarm on 20 JAN.
  • Sent Request for Proposal for NTCRA Sub-Slab Boring Investigation to prospective drilling companies and hosted a site tour.
  • Perimeter air monitoring was suspended during January and will resume prior to commencement of Stage 2 Demolition activities.

December 2015

  • Continued building stabilization activities including interior radiological surveys of buildings and support structures; sealing remaining cracks and floor penetrations;
  • Completed installation of temporary covers on the slabs associated with the Stage 1 Demolition activities;
  • Charter demobilized from the site for winter; building demolition activities are scheduled to resume 1 APR 16;
  • Completed packaging of materials in DOT-approved containers for shipment to EnergySolutions;
  • Completed December shipping campaign: all acid and caustic wastes, DU, and waste oils were transported off site to EnergySolutions in Clive, Utah for disposal.

 

November 2015

  • Performed a site tour for the Agencies on 13 NOV.
  • Continued building stabilization activities, including interior radiological surveys of buildings and support structures; sealing of remaining cracks and floor penetrations;
  • Completed Stage 1 demolition activities, which included demolition of Butler Buildings B1, B2, and B3, the Tank House, Pump House #2, Acetone Shed, Hydrogen Peroxide Shed, compaction dumpster, and gas cylinder shed; demolition debris packaged for off-site disposal;
  • Commenced installation of temporary covers on the slabs of the demolished structures; completed final lock-down of Buildings A and B.
  • Completed November shipping campaign of 34 intermodals containing 353.3 tons to US Ecology Idaho for land disposal.

October 2015

  • Continued Building Stabilization activities, including: interior and exterior radiological surveys of Buildings C, D, and E, removing interior stick-ups from the concrete slab and sealing the remaining cracks and penetrations, applied “lock-down” to surface coatings of walls and floors of ancillary buildings scheduled for demolition as part of Stage 1, installed a new electrical supply to Pump House #1 and new flood lights in the office trailer parking lots, completed utility and vacuum line removal from the Building D contamination reduction zone and mechanical garage, complete a clean-up effort to remove the majority of loose dust on the floors of Buildings C, D, and E.
  • Charter mobilized to the site on 26OCt15 and set up erosion controls around the ancillary buildings scheduled for Stage 1 demolition.
  • Met with Chief of the Concord Fire Department for a tour of the buildings on 23OCT15.
  • Installed propane heaters and tanks in Buildings C and E.
  • Received conditional EPA approval on 20OCT15 for the RTC and Revised Phase 3 Construction Submittal and response to comments.

September 2015

  • Continued Building Stabilization activities, including: vacuuming and wiping down the trusses and ceiling throughout the buildings; began removal of the interior stick-ups from the concrete slab and sealing the remaining cracks and penetrations; completed interior and exterior radiological surveys in Buildings A, B, Butler B1, B2, B3, the Tank house and pump house 2; commenced interior and exterior radiological surveys of Buildings C, D, and E; completed the final lock down of the second floor in Buildings A and B.

August 2015

  • Continued Building Stabilization activities, including: completed loading 12 intermodal containers with the remaining debris generated from the buildings; completed removal of remaining insulation from Building D; completed removal of Building D office mezzanine; completed vacuuming and wiping down the trusses and ceilings in Buildings A and B; commenced vacuuming and wiping efforts in Buildings D and C; commenced radiological surveys of Buildings A and B for the final characterization of the buildings.
  • Heat-stress monitoring efforts continued to protect workers from elevated temperatures.

July 2015

  • All rooftop units and equipment have been removed from the roof, decontaminated, and re-sized. Work in accordance with the Rooftop Systems Removal Work Plan was complete on 16 JUL 2015.
  • Conducted a Geophysical Survey of the Building C Courtyard and northern parking lot. Initial report from the geophysical contractor is that they observed only the one previously identified drum.
  • Continued Building Stabilization activities, including: completed filling and capping of the 1400 ton press and picking area pits; completed removal of utilities from the Building C support area.
  • Completed removal of remaining asbestos containing material that was inaccessible during the initial asbestos abatement. Asbestos tiles were removed from the support area and Building E elevator.
  • Completed the Summer 2015 shipping campaign. Forty (40) containers totaling 731,930 pounds, or 366 tons, were shipped off-site for disposal at US Ecology, Idaho.
  • Submitted Phase 3 Construction Submittal to the agencies for review on 13JUL2015.

June 2015

  • Completed the Spring 2015 shipping campaign with 64 intermodal containers totaling 1.38 million pounds (692 tons) shipped off for disposal at US Ecology in Idaho.
  • Received Agency comments on 11 JUN for the initial Air Monitoring Report.
  • Continued heat-stress monitoring efforts to protect workers due to increasing ambient temperatures.
  • Continued Building Stabilization activities, including solidification of vacuum bags and remaining low-activity wastes; completed additional lab-pack of remaining chemicals; completed cleaning and preparing the 1400 ton press pit to be filled and capped.
  • Continued work pursuant to the Rooftop Systems Removal Work Plan, including mobilizing a crane to remove large HVAC and exhaust units from the buildings and the Building B South courtyard; cleaning and resizing of rooftop systems after removal (Building D interior is complete); completed removal of remaining vacuum lines from the roof and Building B South courtyard.

May 2015

  • Held a site tour for the agencies on 1 MAY 2015.
  • Commenced the Spring 2015 shipping campaign on 11 May 2015 and continued container loading activities. Through the end of May, 56 intermodal containers totaling 1.2 million pounds (609 tons) were shipped off site for disposal at US Ecology, Idaho.
  • Continued rooftop systems removal including mobilizing a crane on site to remove larger rooftop ventilation units, initiating preparation of systems associated with the High-Hazard work areas. Units were inspected for corrosive contamination and neutralized where necessary.
  • Continued building stabilization activities: removed the oven unit from Butler B3; completed removing ancillary equipment and debris from the 1400 ton press pit; removed the remaining heating propane from the 1,000 gallon tanks and removed the 500 gallon propane tank.
  • As ambient temperatures increased, began heat-stress monitoring for worker protection.
  • Continued preparation of Phase 3 Construction Submittal.

April 2015

  • Completed all of the work scoped in the Interior Asbestos Abatement Work Plan. Completed demolition of the non-structural concrete walls throughout Buildings A and B.
  • Continued building stabilization activities: Continued removal of Butler B3 utilities and insulation; completed removal of the office mezzanine, CRZ, and remaining spray on insulation from Building E; completed cleanup and equipment removal from the Building B penthouse and Electrical Room; Completed pumping out of the water from the 1400 ton press pit and began removing the ancillary equipment at the base of the pit.
  • Completed clean-out of the man hole and the 300 ton press pit in Building E; 34 pieces of depleted uranium (DU) were found at the base of the press. The DU was added to the existing inventory for off-site disposal. 
  • Commenced work in accordance with the Rooftop Systems Removal Work Plan. As of 30 APR, all of the vacuum lines and 27 units have been removed from the roof.

March 2015

  • Buildings A, B, and C were closed during beginning of month due to the snow loads on the roof and health and safety concerns. These buildings reopened for regular work activity on 9 MAR.
  • Due to possible electrical problems, the parking lot lights have been shut off until repairs are made or alternative lighting is installed.
  • Building Stabilization activities continued, including completing removal of asbestos piping, tiles, and insulation in Buildings A, B, D, and E; began removing asbestos-containing door caulking from Building D and transite panels/insulation from Building C; completed removal of all interior crane units and utilities from Building E and Butler Buildings B1 and B2; completed cleaning and size reducing the sonodyne unit leaving the bulk portion in place to be removed during the next work phase; completed removal of non-asbestos spray-foam insulation from beneath the Building E mezzanine; commenced non-structural wall demolition in Buildings A and B, completing removal of the second floor walls; completed removal of seven rooftop units from above the Building E Mezzanine (unit E-77 had been dislodged by strong winds prompting early removal).
  • Completed review of Phase 3 Demolition Proposals and selected the demolition contractor.
  • Continued preparation of Phase 3 Construction Submittal.

February 2015

  • Buildings A, B and C were closed to site operations beginning 17 FEB due to the snow loads on the roof. These buildings remained unoccupied throughout the remainder of the month.
  • Shut down the sprinkler system in the Butler B1 and B2 Buildings after meeting with the Concord Fire Department and receiving their permission.
  • Snow removal and site maintenance activities were performed throughout the month.
  • Building Stabilization activities continued, including relocation of the main CRZ and equipment from Building C to Building E to allow access to work areas; completed removal and resizing of two remaining oven units in Building E (originally identified as oversized items to be removed during Phase 3 activities); completed asbestos abatement in Buildings A and B and began constructing containments in Building C; continued solidification of low-level active wastes and remaining inert metal powders and shavings.
  • Continued review of Phase 3 Demolition proposals and provided on site tours to prospective bidders.
  • Continued preparation of Phase 3 Construction Submittal.
  • Submitted revised Phase 2 Construction Submittal, Rooftop Systems Removal Work Plan, and additional Response to Comments on 5 FEB.

January 2015

  • Continued Building Stabilization activities, including completion of removal of utilities in Building D and beginning removal of remaining utilities in Building C, completion of demolition of non-structural concrete walls beneath the C-mezzanine and tool room areas, completion of vacuum cyclone systems removal from Building E Mechanical mezzanine.
  • Completed asbestos abatement from Building A and commenced asbestos abatement in Building B.
  • Completed all work under the High Hazard Work Plan.
  • Began solidifcation of low-level vacuum bags and sonodyne waste.
  • Began identification and characterization of building materials in Buildings C and D.
  • Continued review of Phase 3 demolition proposals and preparation of Phase 3 construction submittal.

December 2014

  • Received Agency comments on Phase 2 Construction Submittal, Appendix F, Rooftop Systems Removal Work Plan on 10 DEC.
  • Received additional Agency comments on the Phase 2 Construction Submittal on 15DEC.
  • Continued Building Stabilization activities, including utility, crane and HVAC removal in Buildings C and D, completed demolition of non-structural concrete walls in the north end of Building C-Mezzanine and the former machine shop, completed demolition of Building D and E mezzanine office partitions and installed necessary guardrails for fall protection, and removal of the floor from the Building B elevator and conduction of a radiological survey at the base of the elevator shaft.
  • Installed an additional sound barrier adjacent to the northern air monitoring station in response to a follow-up noise complaint from a neighboring resident.
  • Continued High Hazard Work Plan activities, including neutralization of impacted materials generated from HF Area work and completed removal of all tanks, ductwork, pumps, and piping associated with the HF processing equipment.
  • Conducted onsite tours of the buildings for prospective demolition contractors responding to the Phase 3 Request for Proposal.
  • Coordinated with the Concord Fire Department as to the cause of the alarms due to a fault in the Building C sprinkler system flow sensor switch, unrelated to NTCRA activities. The switch may be reinstalled once a replacement is located.

November 2014

  • Continued Building Stabilization activities, including utility removal in Buildings C and D, commenced removal of interior corrugated steel walls in the north end of Building D, completed removal of plaster walls and ceilings in Buildings A and B to provide easier access for asbestos abatement, completed removal of acid-tray brackets and the remaining utilities in the vicinity of the acid tray brackets, completed demolition of non-structural concrete walls in the southern portion of Building D near the former pickling and foundry areas, completed demolition of Building D mezzanine office partitions and began demolition of Building E office partitions, installed a sound barrier adjacent to the east air monitoring station in response to a noise complaint from a neighboring resident.
  • Continued High Hazard Work including neutralization of waste generated from Acid Recycling Area and Acid feed lines, began removal and neutralization of equipment from the HF area. Also began removal and neutralization of equipment from the HF area and removed the calciner equipment tanks V-002, V-606, V-608, and V-609.
  • Continued preparation of Phase 3 Construction Submittal.
  • Submitted Response to Comments and Revised Interior Asbestos Abatement Work Plan on 24 NOV and received EPA’s conditional approval on 26NOV.
  • Shipped 32 intermodal containers to US Ecology, Idaho, for land disposal, which included one shipment of lead containing debris. Also loaded and shipped approximately 9,000 gallons of non-hazardous aqueous fluids to US Ecology Idaho.

October 2014

  • Continued Building Stabilization activities, including ductwork and utility removal in Buildings C and D, removed overhead gantry crane throughout Buildings C and D, drained oil from overhead gantry cranes and AC units, demolished non-structural walls in D-116 and Electrical Room, and removed fiberglass walls around Pickling Area.
  • Continued work in accordance with the High Hazard Work Plan including: equipment removal of the acid recycling area, continued neutralization of waste generated from acid recycling area and acid feed lines, and completed removal of the acid feed lines. Acid lines in the HF area were left to be addressed in the next phase of work.
  • Completed solidification of low activity Sonodyne waste.
  • Completed contamination reduction efforts in D-103.
  • Completed exterior survey to identify property boundaries on the southern portion of the site.
  • Continued preparation of Phase 3 Construction Submittal.

September 2014

  • A CREW/2229 Main Street Committee meeting was held on September 17th, 2014.
  • Continued Building Stabilization activities, including ductwork, crane and utility removal in Buildings C and D. Completed ventilation and utility removal around the locker rooms in Building E. Completed demolition work in Building D, Room D-118, including the removal of offices, walkways, and the rotating electrode plasma work area. Completed demolition in Building D, Room D-116. Completed Freon recovery from air conditioning and refrigeration units on rooftops.
  • Completed the preliminary air sampling to establish baseline activity in accordance with the Air Monitoring Plan.
  • Continued work in accordance with the High Hazard Work Plan. The work in the Acid Pickling Area is completed and work commenced this period in the Acid Recycling Area.
  • Continued preparation of the Phase 3 Construction Submittal.
  • Completed the fence installation in the southeast portion of the property to isolate areas where discrete pieces of depleted uranium metal were located during the Depleted Uranium Metal Exterior Site Characterization Survey.
  • Began investigating potential temporary cap materials and vendors for use during building demolition.
  • Submitted the Phase 2 Construction Submittal, Interior Asbestos Abatement Work Plan on 3 SEP 14. Received Agency comments on 22SEP 14.
  • Submitted the Revised Phase 2 Construction Submittal, Rooftop Systems Removal Work and response to Agency comments on 3 SEP 14.
  • Received EPA comments on Perimeter Air Monitoring System on 11 SEP 14 and responded to those comments on 15 SEP 14. Received EPA approval on 17 SEP 14.
  • Received EPA comments on Asbestos Abatement Plan on 22 SEP 14.

August 2014

  • Continued heat stress monitoring to ensure workers are maintaining safe practices, particularly the High-Hazard work crews.
  • Continued Building Stabilization activities, including rooftop system investigations to gather information on equipment dimensions, contamination, and accessibility; continued removal of ductwork and utilities in Buildings D and E; completed clearing and demolition of room E-131 in Building E; and organized and relocated DU materials to former electrical room in Building E for storage.
  • Completed scan of southeast fence line in order to identify areas to be fenced in support of the Exterior Depleted Uranium Exterior Survey Work Plan.
  • Commenced work within the Pickling Area in accordance with the High Hazard Work Plan. Pickling tanks, air scrubber, and most of the associated duct work have been removed and neutralized.
  • Completed installation of the air monitoring stations and equipment. The meteorological station has been calibrated. Installed mufflers on air monitoring stations to reduce exhaust noise. Commenced 30-day background sampling to establish baseline activity in accordance with the Air Monitoring Plan.
  • Completed the latest shipping campaign on 6 AUG 14 of 32 intermodal containers of off-site disposal at US Ecology in Grand View, Idaho.

July 2014

  • Implemented heat stress monitoring to protect workers due to high ambient temperatures in the buildings.
  • Building Stabilization activities continued, including solidification of DU vacuum bag contents and neodymium powders, investigations of rooftop systems, removal of duct work and utilities in Building E, completion of clearing electrical room in Building E, installation of fences around perimeters of air samplers and meteorological tower, and construction of access road to the back side of the boiler room for future asbestos removal operations.
  • Loaded and shipped 20 thirty-two cubic yard intermodal containers off-site for disposal at U.S. Ecology in Idaho.
  • Completed work plans and necessary preparations associated with the High Hazard Work Plan and began work on 28 JUL 2014.
  • Submitted Phase 2 Construction submittal Air Monitoring Plan, revised plan and responses to comments on 23 JUL 14.
  • Submitted the responses to Agency comments and revised Phase 2 Construction Submittal on 31 JUL 14.

June 2014

  • Conducted site tour for Agencies and Concord Fire Department on 2 JUN 2014.
  • Met with Concord Fire Department to discuss High Hazard Work Plan and techniques and safety precautions necessary for first responders in the event of an incident involving hydrofluoric acid.
  • Concord Light investigated a report of downed power line during the installation of the air samplers on 23 JUN 2014. All electrical lines were restored following installation of samplers.
  • Building Stabilization activities continued, including solidification of DU vacuum bag contents and neodymium powders, rooftop systems investigation, vacuuming of underground diesel storage tanks, dismantling and removal of waster water tanks in Building E waste process area, removal of clean-air handling units in Building E Mechanical Room, filtering of waste oils to remove sludge and tranfer into clean drums in a free-release portion of building preparation for disposal and dismantling and removal of pressure washing equipment from Building E.
  • Submitted response to comments on the Notification of High Hazard Materials Removal and Demolition Contractor on 9 JUN 2014 and received verbal approval on 16 JUN 2014.
  • Revised letter request for Fire Alarm System Modifications submitted to Concord Fire Department on 3 JUN 2014. Verbal approval received on 16 JUN 2014.
  • Removed remaining gas cylinders from site on 10 JUN 2014 for off-site disposal at US Ecology.

May 2014

  • Performed necessary community coordination for upcoming High Hazard work: Met with Concord Fire Department to discuss the High Hazard Work Plan and the potential for a hydrofluoric (HF) acid accident; Contacted the Department of Emergency Medicine and Emerson Hospital to evaluate what type of HF acid medical supplies would need to be purchased for the Emergency Room. Also began preparation of contamination reduction zones and equipment for High Hazard work.
  • Continued Building Stabilization activities, including removal of utilities throughout Buildings A and B, completed capping of pits and trenches in Buildings C and D with the exception of the pit containing the 1,400 Ton Press, solidification of DU vacuum bag contents, commenced rooftop system investigation to gather information on equipment dimensions and accessibility, completed sorting and packaging of PCB and non-PCB light ballasts (all contained in vermiculite lined drums now), and completed DU exterior survey for areas not plotted properly in original survey.
  • Poured concrete foundations for placement of air sampling units and meteorological tower. Erected the met tower.
  • Completed packaging and shipment of lab-pack chemicals. Emptied underground storage tanks of all remaining fuel oil and vacuumed out the associated feed lines of residual fuel. Waste oil was disposed off-site by incineration.

April 2014

  • Continued Building Stabilization activities, including removal of utilities throughout Buildings A and B, completed removal of light fixtures and ballasts in Building D, preformed a building-wide cleanup campaign to remove dust and debris generated during previous loading activities, Completed survey of interior pits and trenches prior to starting filling operations, completed filling of pits in Building D, former foundry, and lateral trenches in Building C with gravel and began capping pits and trenches with concrete, inspected the well in Building D and determined depth of about 30 feet and radiological activity between 400k-500k cpm. In addition, completed onsite inspection and identification of non-structural masonry walls throughout Buildings A and B, continued solidification of materials from vacuum bags, completed separation and packaging of lab-pack chemicals, completed depleted uranium exterior survey of catch basins and drains and installed rooftop walkways across Buildings A, B and C for safe access for building maintenance and rooftop system investigations.
  • Submitted a notification of High Hazard Materials Removal and Demolition letter to EPA on 8 Apr 2014.
  • Shipped 8 intermodal containters off-site on 15-16 Apr 2014.

March 2014

  • Continued Building Stabilization activities, including completing removal of remaining combustible walls in Buildings A and B laboratories, continued removal of utilities throughout Building B and lab areas of Building A, dismantled and resized Starmet equipment for disposal (scissor lifts, aerial boom lift and fork lift). Commenced surveying the pits, cracks and penetrations of foundation slabs throughout the buildings. Transferred and containerized acids from the HF area day tanks. Completed draining of lead acid batteries to segregate electrolytes from universal waste.
  • Submitted the Buildings A & B Interior Non-Structural Wall Demolition Letter on 18 MAR 2014 for Agency review.
  • Submitted response to comments and the revised Air Monitoring Plan for Agency review on 27 MAR 2014.
  • Submitted the Rooftop Systems Removal Work Plan on 27 MAR 2014 for Agency review.
  • Shipped 32 intermodal containers off site for disposal during the weeks of 10 MAR and 17 MAR 2014.

February 2014

  • Continued Building Stabilization activities, including snow removal in response to numerous winter weather storms, completion of combustible wall removal in Buildings A except for laboratories, initiated removal of remaining combustible walls in labs, completed removal of piping/conduit from Building C and began removal in Building B, completed removal of vacuum lines in Buildings B and most of E, completed cleaning and removal of lab benches and fume hoods from Building A labs.
  • Completed response to DU fire incident: filled in pits in HF area, segregated and neutralized co-mingled waste piles and supersacks, transferred acids from day tanks to portable poly containers, and neutralized HF area and equipment.
  • Concord Fire Department responded to a fire alarm on 1 Feb 14. Alarm was associated with a sensitive low-flow sensor in Building C, which was corrected by resetting the system. It was determined that the sensor trips with water supply pressure variations in the Concord system and the alarm may continue to be triggered.

January 2014

  • Continued Building Stabilization activities, including completing assembly of rooftop walkways, completing processing and sizing of the crucible router in Building D, continued removal of piping/conduit from Buildings C and D, completed the removal of combustible walls in Building B and initiated removal of combustible walls in Building A, and completed removal of vacuum lines in Buildings A, C, and D and began removal of lines in Buildings B and E.
  • Completed construction of Building E Employee Contamination Reduction Zone (CRZ).
  • Completed implementation of the Tank House Work Plan.
  • Continued the Depleted Uranium Metal Exterior Site Characterization Survey. Remaining activities include the screening of storm water catch basins and is weather dependent.
  • Received Agency comments on Phase 2 Construction submittal on 9 Jan 2014.
  • A small depleted uranium fire occurred during activities related to the High Hazard Materials Removal and Demolition work on 16 Jan 2014. Submitted a letter report to the Agencies on 31 Jan 2014 documenting the event and response.
  • Received Agency approval on 6 Jan 2014 for Filling and Capping of Slab Penetrations letter request.

December 2013

  • Building stabilization activities continued, including processing and sizing disassembled equipment; disposal of Bar Straightener from Building D; removal of lights and ballasts, piping and conduit in Buildings C and D; continued encapsulation of metal powders and shavings; completed cleaning and disassembling of “skull furnace” in Building D; commenced cleaning and disassembling of crucible router in Building D;
  • Submitted response to comments and revised High Hazard Materials Removal and Demolition Plan to Agencies on 2 DEC 13; received Agency approval on 2 DEC 13. Commenced work pursuant to the High Hazard Work Materials Removal and Demolition Plan following approval.
  • Continued the Depleted Uranium Metal Exterior Site Characterization Survey.
  • Submitted letter request to Concord Fire Department for Fire Alarm System Modification on 13 DEC 13.
  • Submitted letter request for Filling and Capping of Slab Penetrations on 12 NOV 13; received additional comments on 30 DEC 13.
  • Continued packaging and loading of intermodal containers. Sixteen containers were shipped during the week of 9 DEC 13. Total shipments by year-end were 154 (152 Containers and 2 Tankers) consisting of 2,956,760 pounds.

November 2013

  • Received Agency comments on High Hazard Work Materials Removal and Demolition Plan on November 25, 2013.
  • Submitted letter request for Filling and Capping of Slab Penetrations on November 12, 2013; received Agency comments on November 25, 2013.
  • Transported 9,205 gallons of liquid to US Ecology from the Tank House activities on November 22, 2013.
  • Concord Public Works responded and repaired a water leak within Pump House #1 that caused potable water to migrate to Route 62 (North Main Street) on November 25, 2013.
  • Continued packaging and loading of intermodal containers.
  • Continued Building Stabilization activities, including demolition of debris and equipment in Buildings C, D, and E; removal of lights and ballasts in Buildings C and D; completion of removal of debris and equipment from trenches in Buildings C and D; commenced encapsulation of metal powders and shavings.
  • Removed approximately 450 gallons of sludge from the North and South tanks in the Tank House and transferred the sludge to drums in preparation for encapsulation. Commenced encapsulation of sludge but halted activities on November 12, 2013 due to freezing conditions with the Tank House. Activities will resume upon installation of a temporary heater.
  • Continued implementation of Depleted Uranium Metal Exterior Site Characterization Survey.
  • Disassembled four oversized Okuma units in Building D. Disassembled and removed sludges/yellow cake from furnaces, ovens, Building B Band Saw and oven base found in Butler B-3. Removed remaining REP machine base and utilities of eastern wall of Building C. Removed all Gantry cranes from former machine shop. Processed and sized for disposal the bar straightener in Building D.

October 2013

  • Received Agency approval on the Tank House Work Plan on October 1, 2013. Work commenced under the plan, including draining of the Building E waste water tanks and Tank House Tanks. Approximately 5,650 gallons were transferred to the frac-tank.
  • Continued Transportation and Disposal off site through October 4, 2013. Total shipped through October was 136 containers with 2,483,460 pounds (1,241 tons). Off-site shipment and disposal will resume in December 2013.
  • Initiated implementation of the Depleted Uranium Metal Exterior Site Characterization Survey.
  • Initiated the encapsulation of metal shavings.
  • Continued packaging and loading of intermodal containers.
  • Continued Building Stabilization activities, including demolition of debris and equipment in Buildings C, D, and E; processing of Butler B-3 debris and materials; removal of vacuum lines in Building D; removal of lights and ballasts in Buildings C and D; completion of metal powders and shavings screening with XRF; removal of combustible walls in Building D and C; initiated removal of debris and equipment from trenches in Buildings C and D.

September 2013

  • Submitted the High Hazard Work Plan for Agency review on September 5, 2013.
  • Provided responses to comments on the Tank House Work Plan on September 23 and 30, 2013.
  • Received Agency verbal approval to proceed on the Metals Solidification SOP on September 16, 2013.
  • Received Agency approval on the Depleted Uranium Metal Exterior Site Characterization Survey Plan on September 25, 2013.
  • Submitted the Phase 2 Construction Report to the Agencies on September 27, 2013.
  • Continued packaging and loading of intermodal containers for off-site waste shipment. Completed the screening of metal powders and shavings with the XRF.
  • Continued demolition of debris and equipment in Building C, D, and E.
  • Commenced processing of Butler B-3 debris and materials in preparation of transportation and disposal.
  • Continued Building Stabilization activities: Commenced removal of vacuum lines and process duct work from machine shop and Building C Mezzanine. Commenced removal of vacuum lines in Building D. Removed QC office in Building E and removed the piping and conduit from the foundry areas. Also initiated light and ballast removal in Buildings C and D along with removal of the electrical switch gear from the back courtyard.

August 2013

  • Continued transportation and disposal of intermodal containers from 6 AUG 13 through 15 AUG 13 with a total amount of waste shipped off-site of 2, 210, 560 pounds (1,105.28 tons) to date.
  • Identified discrete pieces of depleted uranium (DU) metal in the upper two inches of soil covered by vegetation outside the buildings near the former employee entrance during routine radiological monitoring on 3AUG13. Submitted a plan for a DU metal site characterization survey on 27AUG13 to evaluate the soil, asphalt and concrete paved areas around the site not identified for remediation in the Feasibility Study.
  • Continued Building Stabilization activities including disassembling and demolishing equipment in Building C and D foundry areas and partial wall demotion of non-structural combustible walls in Building C. Also moved and staged all debris and materials in Butler Building B-3 into Building D for processing prior to transportation and disposal.

July 2013

  • Continued Building Stabilization activities, including packaging and loading of intermodal containers, removal of oils and fluids from machinery, demolition of debris and equipment in Buildings C, D, and E to assemble higher activity packages to screen with the Radionuclide Detector (RID) unit.
  • Received Agency comments on 17 JUL 13 on the Tank House Plan and Standard Operating Procedure for Stabilization of Metal Powders and Turnings identified in the Phase 1 Construction Submittal.
  • Paused transportation and disposal of intermodal containers from 12 JUL 13 until 5 AUG 13 to allow work crews to stockpile additional waste streams for shipment.
  • Through 31 JUL 13, one hundred and four 32-yard intermodal containers were shipped from the Site with a total weight of 1,797,680 pounds (898.84 tons).

June 2013

  • Held Site walk on 24JUN13 with Agencies, Concord Fire Department, Public Groups, de maximis, and representatives of Respondents to review on-going work activities.
  • Continued Building Stabilization activities, including packaging and loading of intermodal containers, removal of oils and fluids from machinery, demolition of debris and equipment in Buildings C, D, and E, wall removal between D-116 and 117 for efficient loading, and consolidation of usable chemicals and machine oils.
  • Submitted revised USEI Transportation Plan on 13 JUN 13.
  • Submitted the Tank House Plan and Standard Operating Procedure for Stabilization of Metal Powders and Turnings identified in the Phase 1 Construction Submittal to the Agencies on 19 JUN 13.
  • Completed shipment of eighty 32-yard intermodal containers, total weight of approximately 681 tons, for off-site disposal through June 31, 2013.

May 2013

  • Commenced transportation on May 6, 2013, of intermodal containers to US Ecology Inc. for disposal.
  • Waste total shipped for the month of May included forty-eight intermodal containers and 826,080 lbs.
  • Completed labeling of Asbestos Containing Materials (ACM) throughout buildings.
  • Continued the removal of oils and fluids from machinery.
  • Continued packaging of loose debris in Buildings C, D, and E.
  • Continued disassembling and packaging of accessible equipment in Buildings C, D, and E.
  • Completed paving activities as part of the Site Management and Security Plan, Addendum #1.

April 2013

  • Received eight intermodal containers and commenced loading in preparation for shipping in May.
  • Continued building stabilization activities, including commencement of oil and fluid removal from machinery, packing of loose debris in Buildings C, D, and E, disassembly of equipment in Building C and E, and removal of remaining equipment and conduit on wall in Building D, room D117.
  • Continued Site Management and Security Plan Addendum 1 Activities, including repurposing the RI/FS trailer for scale house, relocation of the fence along northwest corner of property around Truck scale, completed electrical installation in scale house, removed and relocated light poles, completed regrading of disturbed areas in preparation for paving, and provided improvements in parking areas for better truck traffic flow.
  • Continued Health and Safety activities, including relocation of the contamination reduction zone in Building C.
  • Submitted RCRA Subtitle C Site Identification and Revised Notification of Hazardous Waste Activity on April 22, 2013.
  • Submitted NTCRA Transportation and Disposal Cost Analysis on April 22, 2013.

March 2013

  • Received EPA approval of the Phase 1 Construction Submittal on March 27, 2013.
  • Removal of northern section of partition wall in Building D, which included removal of the pre-fabricated hallway, the fire suppression system, and the cinder block wall. In addition, relocated the fire alarm conduit and re-energized the garage door motor. Constructed a temporary wall for a contamination reduction zone (CRZ).
  • Completed grading around southern portion of buildings. Placed top soil stockpile immediately south of Butler Building B-2.
  • Packaged loose debris in Building E. Also disassembled equipment in Building E to assemble higher activity packages to screen with the Radionuclide Detector unit.

February 2013

  • Completed radiological screening of laboratory package chemicals in preparation for off-site disposal.
  • Responded to Agency comments on the Phase 1 Construction Submittal comments on February 8, 2013.
  • Began excavation for the truck scale foundation.
  • Performed snow removal for February 10, 2013 snow event of 24 inches. Work crews on-site over the subsequent weekend to maintain access roads.

January 2013

  • Received Agency comments on the response to comments on the Phase 1 Construction and revised Phase 1 Construction submittals.

December 2012

  • EPA approves Addendum No. 1 to Site Management and Security Plan for the NMI NTCRA on December 20, 2012.
  • Continued Building Stabilization activities: installed temporary propane heater in tank house, had Concord Fire Department on site to perform Fire Suppression Loop Pressure Test, and cleared snow following December 17, 2012 snow event.

November 2012

  • Update of NTCRA activities was provided to the Agencies and Concord Fire Department on November 7, 2012.

September 2012

  • On September 10, 2012 de maximis received conditional approval of the Removal Action Work Plans and Cylinder Removal plan pending compliance with final EPA comments.

August 2012

  • On August 27, 2012, de maximis participated in a Site walk with Agencies and Concord Fire Department.
  • de maximis removed Building A HVAC Blower motor unit and patched hole in roof above south stairway on August 15, 2012.
  • Response to Comments, Revised Documents and redlined August 13, 2012.
  • de maximis submitted the Site Management & Security Plan Addendum #1 which summarizes exterior Site improvements for NTCRA Activities on August 14, 2012.
  • Building Stabilization activities performed. Materials were processed and packaged in accordance with the Packaging of Office Contents & Combustible Materials Procedures in the following areas: 1). Building A First Floor- Completed. 2). Building B First Floor- Completed. 3). Building E Office Mezzanine- Completed.

July 2012

  • de maximis received additional comments from the Agencies on Removal Action Work Plan (RAWP) and attachments on July 30, 2012.
  • de maximis submitted the Phase I Construction Submittal on July 27, 2012.
  • de maximis submitted Response to Comments (RTC) on Removal Action Work Plan (RAWP) and attachments on July 2, 2012.
  • Materials were processed and packaged in accordance with the Packaging of Office Contents & Combustible Materials Procedures in the following areas: 1). Building A First Floor- In Progress. 2). Building A Second Floor Office Areas- Completed during July 2012. 3). Building B First Floor- In progress. 4). Building B Second Floor Office Areas- Completed during July 2012. 5). Building C Mezzanine- Completed during July 2012.

June 2012

  • On June 6, EPA provides approval of Packaging Office Contents and Combustible Materials Procedures.
  • During June 2012, de maximis completed execution of Removal Action Work Plan (RAWP) Appendix G- Electrical Termination Plan.

May 2012

  • On May 8, concord Light terminated existing power service to the property/buildings. EPA provides approval of the Electrical Termination Plan and Natural Gas Piping Purge Plan.

April 2012

  • EPA provides comments on the NTCRA Work Plans. de maximis completed installation of Temporary Power Service.

March 2012

  • de maximis starts preparation of “Construction Submittals” the detailed work plans that will address specifically how building contents will be removed for off-site

February 2012

  • de maximis continues inventory of building contents and conducts structural analysis of building roofs.

January 2012

  • NTCRA Work Plans submitted on January 18. de maximis continues to implement measures to reduce risk, and starts comprehensive inventory of building contents.

December 2011

  • EPA approves Interim NTCRA Work Plans on December 19. de maximis continues measures to reduce risk and implements temporary heating of buildings to maintain fire sprinklers and minimize snow load.

November 2011

  • Starmet abandons site on November 2, de maximis takes over responsibility for site security and maintenance. Interim NTCRA Work Plans submitted on November 5. de maximis implements measures to secure buildings and reduce risk. MADPH-RCP terminates Starmet’s licenses to possess radioactive materials on November 8.

September 2011

  • NTCRA Trust funded. Respondents name de maximis, inc. as General Contractor for NTCRA work. de maximis, inc. starts NTCRA planning and identifies subcontractors to assist with NTCRA work.

August 2011

  • Administrative Settlement Agreement and Order on Consent and appendices (together, the Settlement Agreement) for Non-Time-Critical Removal Action (NTCRA) became effective August 9. Respondents to Settlement Agreement name Bruce Thompson as Project Coordinator for NTCRA work.

May 2008

  • Proposed Plan Public Meeting for Engineering Evaluation and Cost Analysis (EE/CA) Disposition of Structures and Contents.

July 2007

  • On July 2007:Revised Draft Engineering Evaluation and Cost Analysis (EE/CA) Disposition of Structures and Contents.

Spring 2007

  • EPAs National Remedy Review Board reviewed the EE/CAs preliminary options and costs for the performance of a Non-Time Critical Removal Action (NTCRA) and provided comments to EPA Region.

October 2006

  • Submitted Draft Engineering Evaluation and Cost Analysis (EE/CA) for the disposition of site structures and building contents for agency review.

June 2006

  • EPA issued Notice to Proceed for an EE/CA for the site buildings and contents.