Total Groundwater Processed Through mid-June, 2019, approximately 1.35 million gallons of groundwater have been processed through the Permanent Groundwater Treatment System (Final Treatment System), which has been operational since April 2, 2019.
Previously, approximately 17 million gallons of groundwater were processed through the Temporary Groundwater Treatment System (TGTS) to maintain hydraulic capture of the plume. The TGTS operated from May 23, 2017 until the Final Treatment System was operational.
Groundwater NTCRA
Updates
Introduction
Building DemolitionNon-Time Critical Removal Action (NTCRA)
Environmental RemediationRemedial Investigation / Feasibility Study (RI/FS)
Quick Links
RSS Feeds
ConstructionEquipmentGuide.com recently published an article about the clean up of Starmet Corporation’s contaminated buildings as part of the NMI NTCRA. Find the 22FEB17 published article link here or download this pdf .
Last updated on January 6, 2021