Through mid-June, 2019, approximately 1.35 million gallons of groundwater have been processed through the Permanent Groundwater Treatment System (Final Treatment System), which has been operational since April 2, 2019.
Previously, approximately 17 million gallons of groundwater were processed through the Temporary Groundwater Treatment System (TGTS) to maintain hydraulic capture of the plume. The TGTS operated from May 23, 2017 until the Final Treatment System was operational.
Photographs of Building C as the clean out progresses. Staging of waste for shipment off site continues with shipment resuming early December.
Last updated on October 11, 2016