Author Archive

Off-site Waste Shipment Ongoing

As of Monday, June 3, forty-eight containers have been shipped offsite, or approximately 446 tons.

Truck hauling waste containers leaving scale house.

Truck hauling waste containers leaving scale house.

Same truck as above leaving site entrance.

Same truck as above leaving site entrance.

 

Shipment of Waste Continues

Twenty-four containers with 406,840 lbs of waste have been shipped off-site as of the close of last week, Friday, May 17th.

First Shipment of Waste Leaves the Site Monday, May 6th

First truck pulling out of the building loaded for waste shipment.

First truck pulling out of the building loaded for waste shipment.

Confirming truck weight while preparing to leave NMI.
Confirming truck weight while preparing to leave NMI.

Gross weight check on waste truck.

Gross weight check on waste truck.First waste disposal truck leaving NMI around 1 pm Monday, May 6, 2013.First waste disposal truck leaving NMI around 1 pm Monday, May 6, 2013.

Shipment Commences of Waste Materials/Building Contents

As part of the building demolition, shipment of waste materials from the building contents for off-site disposal will begin the week of May 6, 2013, in accordance with the EPA approved Phase 1 Construction Submittal. A maximum of six trucks per weekday will depart from the site, avoiding rush hours and school bus hours. Removal of the building contents is scheduled to continue through the end of 2013.

CREW / 2229 Main St. Committee Meeting

CREW / 2229 Main St. Committee met with members of the project team on site at NMI on Wednesday, April 10, 2013.

Phase 1 Construction Submittal Approved March 21, 2013.

Phase 1 Construction Submittal was approved 21MAR2013.

Activities Continue Despite Snow

Grading activities continued during February, as well as excavation for truck scale foundation, despite snow accumulations. During major snowfall events on February 10th, March 8th, and March 19th, snow and ice were removed from driveways, parking lots, sidewalks, and fire hydrants. This allowed for ready access for emergency vehicles and access and egress from buildings as needed. The Truck Scale installation was completed on March 15, 2013.

IMG_3286

Truck scale area during March 8th snow event

IMG-20130312-00138

Installation of truck scale, concrete pad placement.

 

Completing installation of the truck scale.

Completing installation of the truck scale.

 

Disposal Preparation

Continued radiological screening of Laboratory Package Material in preparation for disposal.

Tree Clearing

West Side of Butler Buildings Before OLYMPUS DIGITAL CAMERAOLYMPUS DIGITAL CAMERA

Tree clearing activities continued around west side of Butler Buildings (top left, before), on the southwest side of Building A (right, before) as well as in the Building A courtyard (bottom left, before). Also performed tree stump removal and completed removal of the interior fence south of Building A as part of the Site Management and Security Plan Addendum #1.

After photos:

OLYMPUS DIGITAL CAMERA OLYMPUS DIGITAL CAMERA

West side of Butler Buildings                                     SW corner of Building A

OLYMPUS DIGITAL CAMERAOLYMPUS DIGITAL CAMERA

South end of Building A                                                Building A Courtyard

Site Improvement Work

Mobilized to site last week to begin site improvement work. Started tree clearing on January 21, 2013 following worker site orientation and health and safety briefing. Clearing should continue the rest of this week.

Last updated on May 16, 2013