Rooftop Walkway Installed

Completed installation of walkway system on rooftops of Buildings A, B, and C to provide safe access for building maintenance and rooftop system investigations.Roof Walkway System Building A

Shipping Resumes

An additional eight containers were shipped off-site for disposal on Wednesday, 16 APR 2014.

2229 Main Street Committee and Members of CREW met on site with EPA, Mass DEP

Representatives from EPA, MassDEP and de maximis met with members of CREW and the 2229 Main Street Committee on 9 APR 2014 to discuss the status of the Remedial Investigation and Feasibility Study (RI/FS) and the Non-time Critical Removal Action (NTCRA). The RI/FS discussions included an update regarding an ongoing pilot study of a potential in-situ treatment approach for depleted uranium in groundwater and an update on the anticipated schedule to complete revisions to the Feasibility Study, prepare and issue a Proposed Plan for the Site and the Record of Decision. The NTCRA discussions touched on current work and focused on the draft Air Monitoring Plan and Rooftop Equipment Removal Work Plan.

EPA Approves Remedial Investigation Report and Human Health Risk Assessment

EPA provided approval on 2 APR 2014 for the Remedial Investigation Report and Human Health Risk Assessment. Click here to download the reports and appendices.

Shipping Campaign Complete

The site completed another shipment of waste containers off site for disposal on 19Mar 2014. This round, a total of 32 containers were shipped. Twelve empty containers have been staged on site to be loaded for the next shipping campaign. A total of 186 containers (including 2 tankers) have been shipped to date.

Front view of container shipped on 19 Mar 2014.

Front view of container shipped on 19 Mar 2014.

Meeting with Public Stakeholders to discuss Feasibility Study

Project team met with the Agencies and Public Stakeholder groups on 6 Feb 14 to discuss the Feasibility Study and National Remedy Review Board (NNRB) meeting.

Off-Site Shipment of Waste Resumes

Shipment of waste off-site for disposal resumed this week with 21 containers shipped as of Friday, March 14, 2014.

Building Clean-out Continues

The clean out of the Laboratory and second floor of Building A is now complete. The combustible walls in both Buildings A and B have been removed. The utility clean-out in Building B continues. See NTCRA Progress for photos showing Building C before and after clean-out.

Building Stabilization Activities Continue

Work inside the NMI buildings continues, such as removal of interior vacuum lines from buildings A, B, D, and D; removal of non-structural combustible walls in Buildings A and B; removal of interior utilities such as electrical conduits, process piping, non-process piping and ductwork; and removal of remaining equipment. See NTCRA Progress for photo of Building C Utility Removal.

Tank House Work Complete

The scope of work for the Tank House and Wastewater Treatment Area Work Plan was completed on January 29, 2014. See NTCRA PROGRESS  for progress photos.

High Hazard work has been suspended pending evaluation of findings from the initial work preparations.

Building Stabilization activities continue. Expecting off-site shipping to resume early spring 2014.