2229 Main Street Committee and Members of CREW met on site with EPA, Mass DEP
Representatives from EPA, MassDEP and de maximis met with members of CREW and the 2229 Main Street Committee on 9 APR 2014 to discuss the status of the Remedial Investigation and Feasibility Study (RI/FS) and the Non-time Critical Removal Action (NTCRA). The RI/FS discussions included an update regarding an ongoing pilot study of a potential in-situ treatment approach for depleted uranium in groundwater and an update on the anticipated schedule to complete revisions to the Feasibility Study, prepare and issue a Proposed Plan for the Site and the Record of Decision. The NTCRA discussions touched on current work and focused on the draft Air Monitoring Plan and Rooftop Equipment Removal Work Plan.